Mid-Michigan (MM1) Data Center Electrical Maintenance -5/18/23
Scheduled Maintenance Report for Otava Status Page
Completed
The scheduled maintenance has been completed.
Posted May 18, 2023 - 18:01 EDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted May 18, 2023 - 08:01 EDT
Scheduled
Mid-Michigan (MM1) Data Center Electrical Maintenance -5/18/23
Start Time: 5/18/23 - 8:00 AM EDT
End Time: 5/18/23 - 5:00 PM EDT
Type: Routine
Service Impacting: No - Due to the redundant nature of the design, no impact is expected.
Description: OTAVA® engineers will be conducting routine Electrical maintenance. The building will be placed on generator power for a short time to allow for work to be completed.
If you have any questions or concerns regarding this maintenance, please contact us by logging into https://support.otava.com or calling 877-740-5028, option 3.
MM1 - Genesee County, MI - Data Center Facilities
Posted May 09, 2023 - 09:22 EDT
This scheduled maintenance affected: MM1 - Flint, MI (Mid-Michigan) (Colocation Services (Power, Cooling)).