Austin - Ashburn Data Center ISP Maintenance
Scheduled Maintenance Report for Otava Status Page
Completed
The scheduled maintenance has been completed.
Posted Nov 20, 2021 - 05:00 EST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Nov 20, 2021 - 00:00 EST
Scheduled
Start Time: 11/20/21 - 12:01 AM EST

End Time: 11/20/21 - 5:00 AM EST

Type: Vendor Cabling Replacement

Service Impacting: No - this is the backup circuit

Description: The ISP is replacing DWDM system cabling in Chicago to address flapping on the transport circuit between the Austin and Ashburn data center.

Estimated Downtime: None
Posted Nov 11, 2021 - 10:15 EST
This scheduled maintenance affected: VA4 - Ashburn, VA (Data Center Networking Infrastructure) and AU1 - Austin, TX (Data Center Networking Infrastructure).