Mid Michigan (MM) Data Center UPS Battery Inspection Maintenance Notice - 4/28/2025

Scheduled Maintenance Report for Otava Status Page

Completed

The scheduled maintenance has been completed.
Posted 16 days ago. Apr 28, 2025 - 16:00 EDT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted 17 days ago. Apr 28, 2025 - 08:00 EDT

Scheduled

Mid Michigan (MM) Data Center UPS Battery Inspection Maintenance Notice - 4/28/2025

Start Time: 4/28/25 - 8:00 AM ET

End Time: 4/28/25 - 5:00 PM ET

Type: Routine

Service Impacting: No - Due to the redundant nature of the design, no impact is expected.

Description: OTAVA® engineers, working with vendor engineers, are scheduling a maintenance window to perform maintenance on the UPS Battery system.

If you have any questions or concerns regarding this maintenance, please contact us by logging into https://support.otava.com or calling 877-740-5028, option 3.

MM1 - Genesee County, MI - Data Center Facilities
Posted 22 days ago. Apr 22, 2025 - 11:21 EDT
This scheduled maintenance affected: MM1 - Flint, MI (Mid-Michigan) (Colocation Services (Power, Cooling)).