Otava Cloud Backup Infrastructure Patching (03/22/2023)
Scheduled Maintenance Report for Otava Status Page
Completed
The scheduled maintenance has been completed.
Posted Mar 22, 2023 - 11:00 EDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 22, 2023 - 05:00 EDT
Scheduled
Otava engineers are establishing a maintenance window to perform patching on our Otava Cloud Backup infrastructure at our following datacenter locations :
AU1-Austin
NV1-Las Vegas
IN1-Indianapolis
MM1-Flint
These patches are required in order to continue to provide a secure and compliant environment.

Start Time: 03/22/2023 at 05:00 AM ET.
End Time: 03/22/2023 at 11:00 AM ET.

Service Impacting: Yes - Running backup jobs may fail or be cancelled, new jobs may not start until all services are upgraded and maintenance is complete.

We will kindly ask you to check your backup jobs and restart them if needed once the maintenance window is complete.

Estimated Downtime: Intermittently throughout the maintenance window

If you have any questions or concerns regarding this maintenance please contact us by logging into https://support.otava.com or calling 877-740-5028, option 3.
Posted Mar 07, 2023 - 01:10 EST
This scheduled maintenance affected: AU1 - Austin, TX (OTAVA Cloud Backup), NV1 - Las Vegas, NV (OTAVA Cloud Backup), MM1 - Flint, MI (Mid-Michigan) (OTAVA Cloud Backup), and IN1 - Indianapolis, IN (OTAVA Cloud Backup).