IN1 Data Center Power Interruption - 10/22/26

Incident Report for Otava Status Page

Resolved

At approximately 10:00 AM ET and again at 11:20 AM ET, the IN1 Data Center experienced power interruptions affecting the facility’s power distribution units (PDUs).

The interruptions occurred when a facility vendor caused a power failure while performing break/fix maintenance work. The work has been suspended, and power has been restored. The environment is currently stable.

We will provide additional updates as more information becomes available.
Posted Oct 22, 2026 - 10:00 EDT