Ann Arbor (AA2) Data Center Semi-Annual Fire Systems Preventative Maintenance 5/30/23-5/31/23
Scheduled Maintenance Report for Otava Status Page
Completed
The scheduled maintenance has been completed.
Posted May 31, 2023 - 17:00 EDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted May 30, 2023 - 08:00 EDT
Scheduled
Start Time: 5/30/23 - 8:00 AM EDT

End Time: 5/31/23 - 5:00 PM EDT

Type: Routine

Service Impacting: No - Due to the redundant nature of the design, no impact is expected.

Description: OTAVA® engineers, along with vendor engineers, will be conducting routine Fire System maintenance.

If you have any questions or concerns regarding this maintenance, please contact us by logging into https://support.otava.com or calling 877-740-5028, option 3.

AA2 - Ann Arbor, MI - Building Systems
Posted May 18, 2023 - 11:12 EDT
This scheduled maintenance affected: AA2 - Ann Arbor, MI (Colocation Services (Power, Cooling)).