OTAVA® Austin (AU1) to Ashburn (VA4) Transport Circuit Maintenance - 10/23/2026

Scheduled Maintenance Report for Otava Status Page

Completed

The scheduled maintenance has been completed.
Posted Oct 23, 2026 - 06:00 EDT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 23, 2026 - 01:00 EDT

Scheduled

OTAVA® Austin (AU1) to Ashburn (VA4) Transport Circuit Maintenance - 10/23/2026

Start Time: 10/23/26 - 1:00 AM ET

End Time: 10/23/26 - 6:00 AM ET

Type: Hardware Replacement

Service Impacting: Yes - Up to 2 seconds as the circuit gracefully fails over to the redundant circuit.

Description: Circuit Provider network engineers are replacing hardware on the transport circuit between Austin and Ashburn. During the maintenance windows, the transport circuit between the data centers will not have redundancy.

If you have any questions or concerns regarding this maintenance, please contact us by logging into https://support.otava.com or calling 877-740-5028, option 3.
Posted Oct 15, 2026 - 14:21 EDT
This scheduled maintenance affected: VA4 - Ashburn, VA (Data Center Networking Infrastructure) and AU1 - Austin, TX (Data Center Networking Infrastructure).