Indianapolis (IN1) Uninterruptible Power System Upgrades 2022 - Update
Scheduled Maintenance Report for Otava Status Page
Completed
The scheduled maintenance has been completed.
Posted Dec 06, 2022 - 17:00 EST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Dec 05, 2022 - 08:00 EST
Scheduled
Start Time: 12/05/22 - 8:00 AM EDT

End Time: 12/05/22 - 5:00 PM EDT

Type: UPS/Electrical System Upgrade Maintenance Phase 2

Service Impacting: Low

Description: Otava engineers, along with vendor engineers, will be performing power transfers between the A and B UPS systems. This maintenance will transfer the load from UPS A to UPS B. At this time the Indianapolis data center will be N on its UPS system. This will allow our engineers to remove one old system and replace it with the new upgraded system. This maintenance is required to safely allow the vendor to access and perform work on Otava’s medium voltage tie-ins.

Estimated Downtime: No impact expected.

If you have any questions or concerns regarding this maintenance, please contact us by logging into https://support.otava.com or calling 877-740-5028, option 3.
Posted Nov 21, 2022 - 15:39 EST
This scheduled maintenance affected: IN1 - Indianapolis, IN (Colocation Services (Power, Cooling)).