Metro Detroit (MD1) Data Center Semi Annual Fire Systems Preventative Maintenance Notice (10/17/22)
Scheduled Maintenance Report for Otava Status Page
Completed
The scheduled maintenance has been completed.
Posted Oct 18, 2022 - 17:00 EDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 17, 2022 - 08:00 EDT
Scheduled
Metro Detroit (MD1) Data Center Semi Annual Fire Systems Preventative Maintenance Notice (10/17/22)

Start Time: 10/17/22 - 8:00 AM EDT

End Time: 10/18/22 - 5:00 PM EDT

Type: Fire Systems Semi Annual Preventative Maintenance

Service Impacting: Low

Description: Otava engineers, along with vendor engineers, will be performing preventative maintenance and testing on the MD1 fire systems. This includes the FM-200 system, preaction system, smoke detectors, audible alarms, lights and strobes, leak detection system, and fire extinguishers.

Estimated Downtime: No impact expected

If you have any questions or concerns regarding this maintenance please contact us by logging into https://support.otava.com or calling 877-740-5028, option 3.

MD1 - Westland, MI - Data Center Facilities
Posted Oct 04, 2022 - 13:46 EDT
This scheduled maintenance affected: MD1 - Metro Detroit, MI (Colocation Services (Power, Cooling)).